Construction of Flood Mitigation Structure22CD0049

Construction of Flood Control Structure along San Miguel River, San Agustin to Batasan Bata Section, San Miguel, Bulacan

Construction of Flood Control Structure along San Miguel River, San Agustin to Batasan Bata Section, San Miguel, Bulacan is a DPWH-tracked public work in SAN MIGUEL (BULACAN), BULACAN, Region III. Reported contract value: ₱45,004,286.00. Status: Reported complete (DPWH). Contractor on record: GLOBALCRETE BUILDERS INC. Figures trace to sumbong.

SAN MIGUEL (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱47,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along San Miguel River, San Agustin to Batasan Bata Section, San Miguel, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002899

₱1,891,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002810

₱116,140,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

40 projects · ₱2.7B total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SANTO TOMAS RIVER, SAN FELIPE, ZAMBALES

Region III, Region III

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE & SPECIAL SUPPORT PROGRAM-CONST./IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES & ECONOMIC ZONES-SAN ILDEFONSO-RR STA. AKLE RD. CONNECTING OLD CAGAYAN VALLEY RD. & PULONG SAMPALOC-AKLE-BUASAW RD. IN SUPPORT OF THE AGRIBUSINESSES, DR

Region III, Region III

2018₱166.1M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS, DAANG MAHARLIKA (LZ), INCLUDING ROW, BULACAN 3RD LEGISLATIVE DISTRICT, PROVINCE OF BULACAN

Region III, Region III

2018₱144.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS/DIVERSION ROAD, CANDABA SAN MIGUEL BY-PASS ROAD, PACKAGE 1, INCL. ROW, BULACAN

Bulacan 2nd DEO, Region III

2018₱140.0M
Reported complete (DPWH)

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ANTAYAM-MAPANIQUE CREEK PHASE 6, SAN ILDEFONSO, BULACAN

Region III, Region III

2024₱135.1M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURE ANTAYAM-MAPANIQUE CREEK PHASE 5, SAN ILDEFONSO, BULACAN

Region III, Region III

2024₱135.1M
Past target date (DPWH On-Going)
View all 40 projects →

4. Implementation

Contract Amount

₱45,004,286.00

Progress

Reported complete (DPWH)

Start Date

February 28, 2022

Target End

September 11, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.