Construction of Flood Mitigation Structure23KI0017

Construction of Seawall at the Storm Surge Prone Coastal, Plaridel, Misamis Occidental

Construction of Seawall at the Storm Surge Prone Coastal, Plaridel, Misamis Occidental is a DPWH-tracked public work in PLARIDEL (MISAMIS OCCIDENTAL), MISAMIS OCCIDENTAL, Region X. Reported contract value: ₱47,529,998.48. Status: Reported complete (DPWH). Contractor on record: MINDANAO ROCK. Figures trace to sumbong.

PLARIDEL (MISAMIS OCCIDENTAL), MISAMIS OCCIDENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Aloran River, Barangay Palayan, Aloran, Misamis Occidental
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Misamis Occidental 1st District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,529,998.48

Progress

Reported complete (DPWH)

Start Date

February 26, 2023

Target End

September 14, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.