Flood Control and Drainage19CN0110

CONSTRUCTION OF FLOOD CONTROL FACILITY (GROUTED RIPRAP WITH GABION), PUROK MATAWE, BRGY. PALTIC, DINGALAN, AURORA

CONSTRUCTION OF FLOOD CONTROL FACILITY (GROUTED RIPRAP WITH GABION), PUROK MATAWE, BRGY. PALTIC, DINGALAN, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱14,850,000.00. Status: Reported complete (DPWH). Contractor on record: DALCON CONST. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-19-0014973

₱717,685.00 · FY2019

Released to Division of Davao del Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱14,850,000.00

Progress

Reported complete (DPWH)

Start Date

August 13, 2019

Target End

April 10, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.