Flood Control and Drainage24CC0603

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG HAGONOY RIVER AND ITS TRIBUTARIES AT MARULAO, BARANGAY SANTA ELENA, HAGONOY, BULACAN

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG HAGONOY RIVER AND ITS TRIBUTARIES AT MARULAO, BARANGAY SANTA ELENA, HAGONOY, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱72,373,681.98. Status: Past target date (DPWH On-Going). Contractor on record: WAWAO BUILDERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bagbag Creek, Barangay Pritil, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bulacan 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

164 projects · ₱9.2B total · 15 flags

4. Implementation

Contract Amount

₱72,373,681.98

Progress

Past target date (DPWH On-Going)

Start Date

December 18, 2024

Target End

August 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.