Buildings and Facilities23M00197

CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM) IN BARANGAY POBLACION, AMPATUAN, MAGUINDANAO

CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYMNASIUM) IN BARANGAY POBLACION, AMPATUAN, MAGUINDANAO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱4,752,395.14. Status: Reported complete (DPWH). Contractor on record: H-ROYAL CONST. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,752,395.14

Progress

Reported complete (DPWH)

Start Date

September 18, 2023

Target End

January 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.