Flood Control and Drainage19OC0057

REHABILITATION AND UPGRADING OF DRAINAGE SYSTEM ALONG APITONG STREET, YAKAL STREET, YAKAL ALLEY, TALISAY STREET AND ITS VICINITY, BRGY. COMEMBO,MAKATI CITY, METRO MANILA

REHABILITATION AND UPGRADING OF DRAINAGE SYSTEM ALONG APITONG STREET, YAKAL STREET, YAKAL ALLEY, TALISAY STREET AND ITS VICINITY, BRGY. COMEMBO,MAKATI CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱19,600,000.00. Status: Reported complete (DPWH). Contractor on record: RGDG CONST. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,600,000.00

Progress

Reported complete (DPWH)

Start Date

July 14, 2019

Target End

April 22, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.