Buildings and Facilities19MG0041

CONSTRUCTION OF MULTI-PURPOSE BUILDING (INDIGENOUS PEOPLES CENTER), MUNICIPAL COMPOUND, BRGY. POBLACION, LAKE SEBU, SOUTH COTABATO

CONSTRUCTION OF MULTI-PURPOSE BUILDING (INDIGENOUS PEOPLES CENTER), MUNICIPAL COMPOUND, BRGY. POBLACION, LAKE SEBU, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱1,479,871.41. Status: Reported complete (DPWH). Contractor on record: GOYO CONST. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,479,871.41

Progress

Reported complete (DPWH)

Start Date

July 3, 2019

Target End

September 30, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.