Buildings and Facilities18KK0071

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, SUGBONGCOGON, MISAMIS ORIENTAL

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, SUGBONGCOGON, MISAMIS ORIENTAL is a DPWH-tracked public work in Misamis Oriental 1st DEO, Region X. Reported contract value: ₱4,686,836.80. Status: Reported complete (DPWH). Contractor on record: DCD BUILDERS. Figures trace to dpwh.

Misamis Oriental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,686,836.80

Progress

Reported complete (DPWH)

Start Date

February 20, 2018

Target End

June 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.