Bridges, Roads18N00048

CLUSTER 1- 1.1 CONSTRUCTION OF MISSING LINKS, COMPLETION OF THE EAST-WEST LATERAL ROAD CONNECTING AGUSAN DEL SUR/AGUSAN DEL NORTE TO BUKIDNON, SAMPAGUITA-MAKILOS (AGUSAN DEL SUR/BUKDINON BOUNDARY, BINUCAYAN SECTION, 1.2 CONSTRUCTION OF MISSING LINKS, COMP

CLUSTER 1- 1.1 CONSTRUCTION OF MISSING LINKS, COMPLETION OF THE EAST-WEST LATERAL ROAD CONNECTING AGUSAN DEL SUR/AGUSAN DEL NORTE TO BUKIDNON, SAMPAGUITA-MAKILOS (AGUSAN DEL SUR/BUKDINON BOUNDARY, BINUCAYAN SECTION, 1.2 CONSTRUCTION OF MISSING LINKS, COMP is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱376,195,478.68. Status: Reported complete (DPWH). Contractor on record: MAC BUILDERS CORP FORMERLY: MAC BUILDERS DEVELOPMENT CORP. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱376,195,478.68

Progress

Reported complete (DPWH)

Start Date

August 14, 2018

Target End

May 13, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.