Construction of Flood Mitigation Structure22AF0005

Construction of Flood Control Structure along Bauang River Basin, Sta. 0+000 - Sta. 0+540, Brgys, Calumbaya and Boy-utan, Bauang, La Union

Construction of Flood Control Structure along Bauang River Basin, Sta. 0+000 - Sta. 0+540, Brgys, Calumbaya and Boy-utan, Bauang, La Union is a DPWH-tracked public work in BAUANG (LA UNION), LA UNION, Region I. Reported contract value: ₱44,202,866.82. Status: Reported complete (DPWH). Contractor on record: VILLAR GEN CONST AND SUPPLIES. Figures trace to sumbong.

BAUANG (LA UNION), LA UNION, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱46,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bauang River Basin, Sta. 0+000 - Sta. 0+540, Brgys, Calumbaya and Boy-utan, Bauang, La Union
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003113

₱522,700,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

493 projects · ₱8.0B total · 42 flags

4. Implementation

Contract Amount

₱44,202,866.82

Progress

Reported complete (DPWH)

Start Date

February 17, 2022

Target End

July 27, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.