Flood Control and Drainage25OE0141

REHABILITATION OF DRAINAGE SYSTEM ALONG DAGUPAN ST., MANILA CITY, PHASE 4

REHABILITATION OF DRAINAGE SYSTEM ALONG DAGUPAN ST., MANILA CITY, PHASE 4 is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱9,604,288.89. Status: Past target date (DPWH On-Going). Contractor on record: 1HB CONST CORP FORMERLY: HB CONST. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Sunog Apog, Barangay 172, Manila City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

North Manila DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,604,288.89

Progress

Past target date (DPWH On-Going)

Start Date

March 18, 2025

Target End

September 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.