GAA 2016 MFO-115K00309

REHAB/RECONST./UPGRADING OF DAMAGED PNR INCL DRAINAGE BASED ON PMS/HDM-4 ALONG LINAMON-ZAMB.RD,LDN

REHAB/RECONST./UPGRADING OF DAMAGED PNR INCL DRAINAGE BASED ON PMS/HDM-4 ALONG LINAMON-ZAMB.RD,LDN is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱130,169,051.32. Status: Reported complete (DPWH). Contractor on record: LANAO BUILDER AND ENT 15982. Figures trace to dpwh.

Region X, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱130,169,051.32

Progress

Reported complete (DPWH)

Start Date

March 1, 2016

Target End

October 28, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.