Flood Control and Drainage18K00011

CONST. OF REVETMENT AT GAHUB FCD(UPSTREAM)OF GAHUB BRIDGE RIGHT SIDE ALONG GAHUB RIVER, MIS OR

CONST. OF REVETMENT AT GAHUB FCD(UPSTREAM)OF GAHUB BRIDGE RIGHT SIDE ALONG GAHUB RIVER, MIS OR is a DPWH-tracked public work in Misamis Oriental 1st DEO, Region X. Reported contract value: ₱71,788,229.07. Status: Reported complete (DPWH). Contractor on record: ROAD EDGE TRADING. Figures trace to dpwh.

Misamis Oriental 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱80,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment at Gahub FCD (Upstream )of Gahub Bridge Right Side along Gahub River, Misamis Oriental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-18-0015091

₱0.00 · FY2018

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

223 projects · ₱12.5B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE, BARANGAY GUINACUTAN, VINZ

Region V, Region V

2025₱144.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE ALONG CULASI, BARANGAY PAM

Region V, Region V

2025₱144.9M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUIBAWA RIVER, BANTACAN, NEW BATAAN, DAVAO DE ORO

Davao de Oro 2nd DEO, Region XI

2024₱144.7M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG PORT BARTON-TDC ROAD SECTION, STA. 017+770-STA. 017+865; STA. 017+914-STA. 017+969; STA. 018+023-STA. 018+244, PALAWAN

Region IV-B, Region IV-B

2022₱144.5M
Reported complete (DPWH)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - BUTUAN CITY-CAGAYAN DE ORO CITY-ILIGAN CITY RD - K1398 + 300- K1398 + 600

Misamis Oriental 1st DEO, Region X

2025₱143.3M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF DRAINAGE SYSTEM ALONG DAGUPAN ST., MANILA CITY, PHASE 1

North Manila DEO, National Capital Region

2025₱140.3M
Past target date (DPWH On-Going)
View all 223 projects →

4. Implementation

Contract Amount

₱71,788,229.07

Progress

Reported complete (DPWH)

Start Date

April 22, 2018

Target End

December 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.