Water Provision and Storage22MB0062

CONSTRUCTION OF WATER SYSTEM AT PUROK BALACAYO, BARANGAY OLYMPOG, GENERAL SANTOS CITY

CONSTRUCTION OF WATER SYSTEM AT PUROK BALACAYO, BARANGAY OLYMPOG, GENERAL SANTOS CITY is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱4,931,244.51. Status: Reported complete (DPWH). Contractor on record: HANNA VIA CONST INC FORMERLY:HANNA VIA DESIGN. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Koronadal City, South Cotabato
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

South Cotabato 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,931,244.51

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

June 8, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.