Buildings and Facilities20KJ0071

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAN ISIDRO ALTO, SINACABAN, MISAMIS OCCIDENTAL

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, SAN ISIDRO ALTO, SINACABAN, MISAMIS OCCIDENTAL is a DPWH-tracked public work in Misamis Occidental 2nd DEO, Region X. Reported contract value: ₱951,515.75. Status: Reported complete (DPWH). Contractor on record: 3R'S BUILDERS AND RESOURCES. Figures trace to dpwh.

Misamis Occidental 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱951,515.75

Progress

Reported complete (DPWH)

Start Date

September 7, 2020

Target End

November 10, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.