Water Provision and Storage23AF0173

CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS), STO. TOMAS, TUBAO, AGOO, ARINGAY, BAUANG, AND BURGOS, LA UNION

CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS), STO. TOMAS, TUBAO, AGOO, ARINGAY, BAUANG, AND BURGOS, LA UNION is a DPWH-tracked public work in La Union 2nd DEO, Region I. Reported contract value: ₱2,313,886.87. Status: Reported complete (DPWH). Contractor on record: KRYPTONITE 6S BUILDERS INC. Figures trace to dpwh.

La Union 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System at San Simon East, Aringay, La Union
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

La Union 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,313,886.87

Progress

Reported complete (DPWH)

Start Date

August 30, 2023

Target End

November 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.