Construction of Flood Mitigation Structure22FH0020

Construction of Breakwater (Phase 2), Bagamanoc, Catanduanes

Construction of Breakwater (Phase 2), Bagamanoc, Catanduanes is a DPWH-tracked public work in BAGAMANOC (CATANDUANES), CATANDUANES, Region V. Reported contract value: ₱9,793,940.02. Status: Reported complete (DPWH). Contractor on record: NIDA BUILDER'S & SUPPLIES. Figures trace to sumbong.

BAGAMANOC (CATANDUANES), CATANDUANES, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Barangay Mabini, Caramoran, Catanduanes
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002935

₱453,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003057

₱60,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002736

₱30,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006801

₱30,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001786

₱20,000,000.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱9,793,940.02

Progress

Reported complete (DPWH)

Start Date

March 2, 2022

Target End

October 26, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.