Roads16LG0006

REHAB./ IMPROVEMENT OF LANGKA - LUBAN- CABUAYA ROAD, CITY OF MATI, DAVAO ORIENTAL

REHAB./ IMPROVEMENT OF LANGKA - LUBAN- CABUAYA ROAD, CITY OF MATI, DAVAO ORIENTAL is a DPWH-tracked public work in Davao Oriental 2nd DEO, Region XI. Reported contract value: ₱48,909,907.51. Status: Reported complete (DPWH). Contractor on record: MAER SUMMIT KONSTRUKT CO. Figures trace to dpwh.

Davao Oriental 2nd DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control - Barangay Mayo, Mati, Davao Oriental
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0033564

₱19,191.00 · FY2016

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱48,909,907.51

Progress

Reported complete (DPWH)

Start Date

March 7, 2016

Target End

July 24, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.