Construction of Flood Mitigation Structure23GE0010

Construction of Flood Control System in Baragnay Cabalagnan, Nueva Valencia, Guimaras

Construction of Flood Control System in Baragnay Cabalagnan, Nueva Valencia, Guimaras is a DPWH-tracked public work in NUEVA VALENCIA (GUIMARAS), GUIMARAS, Region VI. Reported contract value: ₱57,868,773.82. Status: Reported complete (DPWH). Contractor on record: ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP. Figures trace to sumbong.

NUEVA VALENCIA (GUIMARAS), GUIMARAS, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Facility, Barangay Rizal, Jordan, Guimaras
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Guimaras District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱57,868,773.82

Progress

Reported complete (DPWH)

Start Date

February 17, 2023

Target End

November 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.