Roads17IF0044

NETWORK DEVELOPMENT - IMPROVEMENT/ WIDENING OF NATIONAL ROADS - SECONDARY PALOMPON - ISABEL - MERIDA - ORMOC ROAD, K1107+093 - K1108+605, K1108+605 - K1110+134

NETWORK DEVELOPMENT - IMPROVEMENT/ WIDENING OF NATIONAL ROADS - SECONDARY PALOMPON - ISABEL - MERIDA - ORMOC ROAD, K1107+093 - K1108+605, K1108+605 - K1110+134 is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱84,846,675.40. Status: Reported complete (DPWH). Contractor on record: JA ACHACOSO ENT. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pagsanga-an Flood Control, Brgy. Lilo-an, Ormoc City, Leyte
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-17-0021054

₱487,933.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

132 projects · ₱3.0B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION OF THE REGIONAL CULTURAL HUB, PHASE I, TAGBILARAN CITY, BOHOL PROVINCE

Region VII, Region VII

2021₱135.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE, PACKAGE 2, BARANGAY STO NIÑO - BARANGAY MINDANAO, MALABU

Cebu 7th DEO, Region VII

2025₱97.5M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING PALOMPON - ISABEL - MERIDA - ORMOC ROAD K1098+000 - K1101+416

Leyte 4th DEO, Region VIII

2018₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SPECIAL ROAD FUND - MOTOR VEHICLE USERS CHARGE (MVUC) - AS PER R.A. 11239, CONSTRUCTION AND INSTALLATION OF SOLAR STREETLIGHTS, SAFETY SIGNS AND DEVICES - K0065+000 - K0072+000, ARGAO, CEBU

Cebu 2nd DEO, Region VII

2021₱96.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF SHORELINE PROTECTION STRUCTURES - JCT. HIMAY-ANGAN - SILAGO - ABUYOG BDRY. RD. (S00228LT) - ALONG ST. BERNARD SECTION, SOUTHERN LEYTE

Region VIII, Region VIII

2023₱89.8M
Past target date (DPWH On-Going)

CONSTRUCTION OF SHORELINE PROTECTION STRUCTURE - JCT. HIMAY-ANGAN - SILAGO - ABUYOG BDRY. RD. - (S00228LT) ALONG SAN JUAN SECTION, SOUTHERN LEYTE

Region VIII, Region VIII

2023₱85.6M
Reported complete (100% progress, DPWH status On-Going)
View all 132 projects →

4. Implementation

Contract Amount

₱84,846,675.40

Progress

Reported complete (DPWH)

Start Date

April 18, 2017

Target End

February 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.