Construction of Flood Mitigation Facility24OE0037

Installation of Booster Pump at Estero de Magdalena, Soler Section (Package 2b), Tondo, Manila City

Installation of Booster Pump at Estero de Magdalena, Soler Section (Package 2b), Tondo, Manila City is a DPWH-tracked public work in CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region. Reported contract value: ₱72,374,032.61. Status: Reported complete (DPWH). Contractor on record: AL-AMEN BUILDERS. Figures trace to sumbong.

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Binondo, Barangay 281, Manila City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0002185

₱40,000,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008748

₱1,545,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0008763

₱142,000.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

74 projects · ₱1.8B total · 0 flags

Other projects by this contractor

No sat.

INSTALLATION OF SOLAR LED STREETLIGHTS WITHIN BARANGAYS 649 TO 828, PRES. QUIRINO AVE (FROM TAFT AVE. TO SOUTH SUPERHIGHWAY), SOUTH SUPERHIGHWAY (FROM ZOBEL ROXAS ST. TO P. QUIRINO AVE), P. FAURA ST. (SAN MARCELINO ST. TO ROXAS BLVD.), ESCODA ST. (FROM TA

South Manila DEO, National Capital Region

2025₱145.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE OF ESTERO DE PACO, MANILA CITY PHASE 2

South Manila DEO, National Capital Region

2025₱143.2M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2:PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODS-FLOOD MGM'T PROGRAM-CONST./MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEMS-CONST. OF SLOPE PROTECTION STRUCTURE OF ESTERO DE PACO, MANILA CITY PHASE 1

South Manila DEO, National Capital Region

2025₱143.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SLOPE PROTECTION STRUCTURE ALONG PAGASA SABLAYAN TO VICTORIA ROAD, PALSIKAYON SECTION (PHASE 1), OCC. MINDORO

Region IV-B, Region IV-B

2023₱96.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SLOPE PROTECTION STRUCTURE ALONG PAGASA SABLAYAN TO VICTORIA ROAD, PALSIKAYON SECTION (PHASE 2), OCC. MINDORO

Region IV-B, Region IV-B

2023₱96.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF SLOPE PROTECTION STRUCTURE ALONG PAGASA SABLAYAN TO VICTORIA ROAD, PALSIKAYON SECTION (PHASE 3), OCC. MINDORO

Region IV-B, Region IV-B

2023₱96.5M
Reported complete (DPWH)
View all 74 projects →

4. Implementation

Contract Amount

₱72,374,032.61

Progress

Reported complete (DPWH)

Start Date

February 8, 2024

Target End

June 23, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.