Roads22JB0003

CONSTRUCTION OF CONCRETE ROAD -JCT. DIPOLOG-SINDANGAN ROAD CONNECTING TO BAGO-DALONGDONG (JOAQUIN MACIAS) IN SUPPORT OF RICE, RUBBER, COCONUT AND ABACA INDUSTRIES, SINDANGAN, ZAMBOANGA DEL NORTE.

CONSTRUCTION OF CONCRETE ROAD -JCT. DIPOLOG-SINDANGAN ROAD CONNECTING TO BAGO-DALONGDONG (JOAQUIN MACIAS) IN SUPPORT OF RICE, RUBBER, COCONUT AND ABACA INDUSTRIES, SINDANGAN, ZAMBOANGA DEL NORTE. is a DPWH-tracked public work in Zamboanga del Norte 2nd DEO, Region IX. Reported contract value: ₱9,557,962.02. Status: Reported complete (DPWH). Contractor on record: ESR CONST AND DEVELOPMENT CORP FORMERLY: ESR CONST. Figures trace to dpwh.

Zamboanga del Norte 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,621,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Left Bank of Dohinob River (Upstream and Downstream), San Antonio, Manukan, Zamboanga del Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Zamboanga del Norte 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

335 projects · ₱24.0B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF CONCRETE ROAD AND ROAD SLOPE PROTECTION STRUCTURE BALIGUIAN COASTAL ROAD, JUNCTION BALIGUIAN - KAUSWAGAN - MAMAD SECTION, ZAMBOANGA DEL NORTE, 2ND DEO, K2043+170.00 - K2044+410.00, K2044+810.00 - K2046+464.00, NET LENGTH: 5.79 LANE KM/2,8

Region IX, Region IX

2018₱280.6M
Reported complete (DPWH)
No sat.

CONCRETING OF ZAMBOANGA DEL SUR COASTAL ROAD, ZAMBOANGA DEL SUR (2ND DEO), CHAINAGE 0 - CHAINAGE 3008.75; CHAINAGE 6000 - CHAINAGE 7542.78; CHAINAGE 28510 - CHAINAGE 29558.80; CHAINAGE 97 - CHAINAGE 1097; CHAINAGE 940.00 - CHAINAGE 1979.62; CHAINAGE 21157

Region IX, Region IX

2016₱276.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS LABANGAN - PAGADIAN CITY - DUMALINAO ZDS BY-PASS ROAD, INCLUDING ROW, ZAMBOANGA DEL SUR

Region IX, Region IX

2018₱215.6M
Reported complete (DPWH)
No sat.

CONCRETING OF ROAD LUUK - PANAMAO - PATIKUL CIRCUMFERENTIAL ROAD, SULU 2ND LD, STA. 5+000.00 - STA. 10+280.00 (NET LENGTH: 5,280.00 LN.M.)

Region IX, Region IX

2016₱202.5M
Reported complete (DPWH)
No sat.

ROAD WIDENING DIPOLOG - SINDANGAN - LILOY ROAD, ZAMBOANGA DEL NORTE 1ST DEO, K1873+862.00 - K1875+233.00, K1875+377.00 - K1877+534.00, K1881+560.00 - K1884+449.95, K1884+449.95 - K1885+210.00, NET LENGTH: 14.36 LANE KM/7,178.00 LN.M./7.178 KM

Region IX, Region IX

2018₱187.1M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD ALONG NRJ BARANGAY CAMUL - NRJ BARANGAY LUMBAYAO PACKAGE 2, ZAMBOANGA DEL NORTE

Region IX, Region IX

2024₱173.6M
Past target date (DPWH On-Going)
View all 335 projects →

4. Implementation

Contract Amount

₱9,557,962.02

Progress

Reported complete (DPWH)

Start Date

March 31, 2022

Target End

May 29, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.