Roads24FB0043

BIP: ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY CANAROM TO BARANGAY SAN RAMON, DARAGA, ALBAY (PACKAGE 5)

BIP: ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY CANAROM TO BARANGAY SAN RAMON, DARAGA, ALBAY (PACKAGE 5) is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱28,810,590.52. Status: Past target date (DPWH On-Going). Contractor on record: FEDERAL AGGREGATES AND DEVELOPMENT CORP. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱38,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Barangay Namantao, Daraga, Albay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Albay 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

10 projects · ₱260.3M total · 1 flags

Other projects by this contractor

No sat.

BIP: ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY CANAROM TO BARANGAY SAN RAMON, DARAGA, ALBAY (PACKAGE 2)

Albay 2nd DEO, Region V

2024₱28.8M
Past target date (DPWH On-Going)
No sat.

BIP: ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, BARANGAY CANAROM TO BARANGAY SAN RAMON, DARAGA, ALBAY (PACKAGE 3)

Albay 2nd DEO, Region V

2024₱28.8M
Past target date (DPWH On-Going)
No sat.

BIP: ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION OF ROAD, BARANGAY CANAROM TO BARANGAY SAN RAMON, DARAGA, ALBAY (PACKAGE 4)

Albay 2nd DEO, Region V

2024₱28.8M
Past target date (DPWH On-Going)
No sat.

CLUSTER 14 - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES

Albay 2nd DEO, Region V

2024₱28.5M
Past target date (DPWH On-Going)
No sat.

CLUSTER 7 - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES

Albay 2nd DEO, Region V

2024₱28.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1-ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-DARAGA URBAN TOURISM ECO ROUTE PROJECT, PACKAGE 3, ALBAY, DARAGA, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2025₱26.9M
Past target date (DPWH On-Going)
View all 10 projects →

4. Implementation

Contract Amount

₱28,810,590.52

Progress

Past target date (DPWH On-Going)

Start Date

March 20, 2024

Target End

August 19, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.