Flood Control and Drainage20AD0082

CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE-SANTA SEAWALL, PASUNGOL BUCALAG SECTION, SANTA, ILOCOS SUR

CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE-SANTA SEAWALL, PASUNGOL BUCALAG SECTION, SANTA, ILOCOS SUR is a DPWH-tracked public work in Ilocos Sur 2nd DEO, Region I. Reported contract value: ₱27,724,309.62. Status: Reported complete (DPWH). Contractor on record: M V SABALBURO CONST AND SUPPLY. Figures trace to dpwh.

Ilocos Sur 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱27,724,309.62

Progress

Reported complete (DPWH)

Start Date

October 12, 2020

Target End

May 29, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.