Buildings and Facilities24CB0056

CONSTRUCTION OF MULTI-PURPOSE BUILDING (WORSHIP HALL), BARANGAY SAINT FRANCIS I, LIMAY, BATAAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING (WORSHIP HALL), BARANGAY SAINT FRANCIS I, LIMAY, BATAAN is a DPWH-tracked public work in Bataan 2nd DEO, Region III. Reported contract value: ₱10,833,115.37. Status: Past target date (DPWH On-Going). Contractor on record: E R VENZON CONST 19013. Figures trace to dpwh.

Bataan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure ( Phase I ) , Barangay Pantingan, Pilar, Bataan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Bataan 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱10,833,115.37

Progress

Past target date (DPWH On-Going)

Start Date

April 30, 2024

Target End

November 25, 2024

5. Audit