Roads25DN0001

FY 2025 DPWH INFRASTRUCTURE PROGRAM - ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - TAYTAY DIV RD - K0023+060 - K0023+485, RIZAL (FIRST DISTRICT)

FY 2025 DPWH INFRASTRUCTURE PROGRAM - ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - TAYTAY DIV RD - K0023+060 - K0023+485, RIZAL (FIRST DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱31,360,000.00. Status: Reported complete (DPWH). Contractor on record: READYCON TRADING. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Taytay River, Barangay San Isidro, Taytay, Rizal
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Rizal 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱31,360,000.00

Progress

Reported complete (DPWH)

Start Date

February 11, 2025

Target End

April 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.