Flood Control and Drainage22DJ0061

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS, CONSTRUCTION OF DUMACAA RIVER FLOOD CONTROL, BRGY. 11, LUCENA CITY, QUEZON

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS, CONSTRUCTION OF DUMACAA RIVER FLOOD CONTROL, BRGY. 11, LUCENA CITY, QUEZON is a DPWH-tracked public work in Quezon 2nd DEO, Region IV-A. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: I A BOSQUE CONST CORP 12597. Figures trace to dpwh.

Quezon 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dumacaa River Flood Control, Brgy. 11, Lucena City, Quezon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Quezon 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 12597

205 projects · ₱5.6B total · 0 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF IYAM RIVER FLOOD CONTROL STRUCTURE, PACKAGE 5, LUCE

Quezon 2nd DEO, Region IV-A

2025₱137.1M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONSTRUCTION OF MISSING LINKS/NEW ROADS, EXTENSION OF QUEZON ECO-TOURISM-SARIAYA-CANDELARIA-TIAONG-SAN ANTONIO ROAD, SAN ANTONIO SECTION, SAN

Quezon 2nd DEO, Region IV-A

2020₱125.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/ FACILITIES, CONSTRUCTION OF DUMACAA RIVER FLOOD CONTROL (PACKAGE 11), LUCENA CITY, QUEZON

Quezon 2nd DEO, Region IV-A

2023₱96.5M
Past target date (DPWH On-Going)
No sat.

OFF-CARRIAGEWAY IMPROVEMENT: SHOULDER PAVING/CONSTRUCTION - GUMACA-PITOGO-MULANAY-SN NARCISO RD- K0213+000 - K0213+853, K0214+140 - K0214+235, K0215+ -514 - K0216+316, K0216+355 - K0217+014, K0217+027 - K0218+000, K0222+000 -K0224+000, K0225+000 - K0226+

Quezon 3rd DEO, Region IV-A

2018₱96.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF QUEZON INDUSTRIAL HIGHWAY (

Quezon 2nd DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF QUIAPO RIVER FLOOD CONTROL (PACKAGE 1), CANDELARIA, QUEZON

Quezon 2nd DEO, Region IV-A

2024₱96.5M
Reported complete (DPWH)
View all 205 projects →

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 24, 2022

Target End

May 8, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.