Construction of Revetment24CC0043

Construction of Revetment along Balagtas River, Santol, Balagtas, Bulacan

Construction of Revetment along Balagtas River, Santol, Balagtas, Bulacan is a DPWH-tracked public work in BALAGTAS (BIGAA) (BULACAN), BULACAN, Region III. Reported contract value: ₱49,499,812.33. Status: Reported complete (DPWH). Contractor on record: M G FRANCISCO CONST. Figures trace to sumbong.

BALAGTAS (BIGAA) (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Balagtas River, Barangay San Juan, Purok 4 - Purok 5, Balagtas, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017916

₱440,428.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007285

₱1,480,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005756

₱95,671.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007286

₱137,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005755

₱1,178,933.00 · FY2024

Source

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24CC0043-Construction of Revetment along Balagtas

₱47,519,951.06 · M. G. FRANCISCO CONSTRUCTION

4. Implementation

Contract Amount

₱49,499,812.33

Progress

Reported complete (DPWH)

Start Date

March 20, 2024

Target End

November 14, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.