Water Provision and Storage19GK0255

CONSTRUCTION OF WATER SUPPLY SYSTEMS- CONSTRUCTION/REHABILITATION OF WATER SYSTEM (LEVEL 2), BARANGAY TOMONGTONG, EB MAGALONA, NEGROS OCCIDENTAL

CONSTRUCTION OF WATER SUPPLY SYSTEMS- CONSTRUCTION/REHABILITATION OF WATER SYSTEM (LEVEL 2), BARANGAY TOMONGTONG, EB MAGALONA, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 1st DEO, Negros Island Region. Reported contract value: ₱3,291,189.10. Status: Reported complete (DPWH). Contractor on record: R A G CORONA CONST AND AGGREGATES SUPPLY. Figures trace to dpwh.

Negros Occidental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,291,189.10

Progress

Reported complete (DPWH)

Start Date

September 10, 2019

Target End

February 4, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.