CONSTRUCTION OF BRIDGE - CONSTRUCTION OF MARIA CARIDAD BRIDGE, POBLACION MA. CARIDAD, ARAKAN, NORTH COTABATO is a DPWH-tracked public work in Cotabato 2nd DEO, Region XII. Reported contract value: ₱77,200,000.00. Status: Reported complete (DPWH). Contractor on record: THREE W BUILDERS INC 10722. Figures trace to dpwh.

Cotabato 2nd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Malasila River Flood Control L/S , Brgy. Sta. Filomina and Brgy. Poblacion Section, Makilala, North Cotabato
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Cotabato 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱77,200,000.00

Progress

Reported complete (DPWH)

Start Date

March 29, 2021

Target End

April 17, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.