Roads24GI0047

PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO-CAPIZ RD (NEW ROUTE) - K0012 + 993 - K0013 + 543

PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - ILOILO-CAPIZ RD (NEW ROUTE) - K0012 + 993 - K0013 + 543 is a DPWH-tracked public work in Iloilo 4th DEO, Region VI. Reported contract value: ₱19,539,164.55. Status: Reported complete (DPWH). Contractor on record: F GURREA CONST INC. Figures trace to dpwh.

Iloilo 4th DEO, Region VI
Region: Region VI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱99,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Aganan Flood Control Structure ( Jaro - Aganan River ) , Barangay Balabago, Alimodian, Iloilo
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Iloilo 4th DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,539,164.55

Progress

Reported complete (DPWH)

Start Date

June 21, 2024

Target End

September 2, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.