Buildings and Facilities17JI0125

CONSTRUCTION (COMPLETION) OF TWO (2) UNITS TWO(2) STOREY -TEN (10) CLASSROOM SCHOOL BUILDING AT MALANGAS NHS, MALANGAS, ZAMBOANGA SIBUGAY

CONSTRUCTION (COMPLETION) OF TWO (2) UNITS TWO(2) STOREY -TEN (10) CLASSROOM SCHOOL BUILDING AT MALANGAS NHS, MALANGAS, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 1st DEO, Region IX. Reported contract value: ₱161,670.00. Status: Reported complete (DPWH). Contractor on record: HENSO CONST INC. Figures trace to dpwh.

Zamboanga Sibugay 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,215,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Imelda-Bayog-Kumalarang-Lapuyan-Margosatubig Road, part of Sibuguey River, (K1763+245 - K1763+510), Barangay Pilar, Diplahan, Zamboanga Sibugay
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-17-0020611

₱82,422.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱161,670.00

Progress

Reported complete (DPWH)

Start Date

September 4, 2017

Target End

September 8, 2017

5. Audit