Construction of Flood Mitigation Structure22DI0106

Construction of Riverwall, Biñan River near Barangay San Vicente (Staggered), Biñan City, Laguna

Construction of Riverwall, Biñan River near Barangay San Vicente (Staggered), Biñan City, Laguna is a DPWH-tracked public work in CITY OF BIÑAN (LAGUNA), LAGUNA, Region IV-A. Reported contract value: ₱48,994,072.94. Status: Reported complete (DPWH). Contractor on record: ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP. Figures trace to sumbong.

CITY OF BIÑAN (LAGUNA), LAGUNA, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment/Floodwall (Staggered), Bi±an City, Laguna
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002907

₱1,026,969,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003022

₱159,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-22-0007547

₱51,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002753

₱40,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱48,994,072.94

Progress

Reported complete (DPWH)

Start Date

July 5, 2022

Target End

August 19, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.