Buildings and Facilities23CK0013

CONSTRUCTION OF CAMP SECURITY FENCE, ARMOR DIVISION, PA, CAMP O'DONELL, CAPAS, TARLAC

CONSTRUCTION OF CAMP SECURITY FENCE, ARMOR DIVISION, PA, CAMP O'DONELL, CAPAS, TARLAC is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱24,486,568.32. Status: Reported complete (DPWH). Contractor on record: R M DELA CRUZ CONST. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Cubcub, Mayantoc, Tarlac
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Tarlac 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

42 projects · ₱621.0M total · 0 flags

4. Implementation

Contract Amount

₱24,486,568.32

Progress

Reported complete (DPWH)

Start Date

March 14, 2023

Target End

August 10, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.