GAA 2017 LFP17CD0124

IMPROVEMENT/REPAIR/REHABILITATION OF EXISTING MULTI-PURPOSE BUILDING, SAN LORENZO, NORZAGARAY, BULACAN

IMPROVEMENT/REPAIR/REHABILITATION OF EXISTING MULTI-PURPOSE BUILDING, SAN LORENZO, NORZAGARAY, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱1,880,992.00. Status: Reported complete (DPWH). Contractor on record: EIRISH BUILDERS. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement/Repair/Rehabilitation of existing Flood Control of Zamora Pumping Station and its tributaries, Barangay Zamora, Meycauayan, Bulacan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-17-0015191

₱481,100.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

126 projects · ₱3.4B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF ROAD,PHASE II,SITIO TALAMSI I-SITIO KAMB

Bulacan 3rd DEO, Region III

2025₱142.5M
Past target date (DPWH On-Going)
No sat.

CONVERGE. AND SPECIAL SUPPORT PROG. - SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGSS/ FACILITIES - CONST.OF ROAD, PHASE I, SITIO TALAMSI I - SITIO KAM

Bulacan 3rd DEO, Region III

2025₱142.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), ANGAT, BULACAN

Bulacan 2nd DEO, Region III

2023₱117.5M
Reported complete (DPWH)
No sat.

STATE UNIVERSITIES AND COLLEGES (SUCS)-ESTABLISHMENT AND/OR SUPPORT TO THE COLLEGE OF MEDICINES, SAN RAFAEL CAMPUS-BULACAN STATE UNIVERSITY, SAN RAFAEL, BULACAN, PROVINCE OF BULACAN

Region III, Region III

2024₱98.5M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, LONGOS - ZAMORA SECTION, STA. 06+220 - STA. 06+340, MEYCAUAYAN, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, CITY COLLEGE OF SAN JOSE DEL MONTE SCHOOL OF NURSING AND ALLIED HEALTH (PHASE 2), BARANGAY MINUYAN PROPER, CITY OF SAN JOSE DEL MONTE, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.0M
Past target date (DPWH On-Going)
View all 126 projects →

4. Implementation

Contract Amount

₱1,880,992.00

Progress

Reported complete (DPWH)

Start Date

March 30, 2017

Target End

June 22, 2017

5. Audit