Roads19OE0112

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM:ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS MORIONES - (S02344LZ) K0004 + 789 - K0005 + 080.30

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM:ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS MORIONES - (S02344LZ) K0004 + 789 - K0005 + 080.30 is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱2,537,198.40. Status: Reported complete (DPWH). Contractor on record: ALLEYWAY CONST. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-19-0005535

₱3,306,000.00 · FY2019

Released to Regional Office - XI (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

49 projects · ₱1.0B total · 1 flags

Other projects by this contractor

No sat.

MFO 2-FLOOD MANAGMENT SERVICES CONSTRUCTION/MAINTENANCE OF LOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM: DRAINAGE IMPROVMENT ALONG YUSECO (INCLUDING KABULUSAN OUT FALL) TONDO, MANILA

North Manila DEO, National Capital Region

2017₱48.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-LOCAL ROADS AND BRIDGES-LOCAL ROADS-REHABILITATION OF ROAD WITH DRAINAGE IMPROVEMENT AND PATHWAYS, ZONE 1, 2, & 3, MANILA CITY

North Manila DEO, National Capital Region

2018₱47.8M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL- PROJECTS - LOCAL ROADS AND BRIDGES - LOCAL ROADS - REHABILITATION OF ROAD WITH DRAINAGE IMPROVEMENT AND PATHWAYS, ZONE 4, 5 & 6, MANILA CITY

North Manila DEO, National Capital Region

2018₱47.5M
Reported complete (DPWH)
No sat.

Rehabilitation of Drainage System at Zone 1-12, Tondo, Manila City

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region

2022₱47.5M
Reported complete (DPWH)
No sat.

MFO 2 - FLOOD MANAGEMENT SERVICES CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS CONSTRUCTION OF FLOOD MITIGATION/STRUCTURES AND DRAINAGE SYSTEMS - M. EARNSHAW AND GOV. FORBES STREET, SAMPALOC, MANILA SAMPALOC, MANILA CITY

North Manila DEO, National Capital Region

2017₱46.3M
Reported complete (DPWH)
No sat.

REHABILITATION / IMPROVEMENT OF ROADS AND ALLEYS INCLUDING DRAINAGE, BRGY. 1-146, MANILA CITY

North Manila DEO, National Capital Region

2020₱39.6M
Reported complete (DPWH)
View all 49 projects →

4. Implementation

Contract Amount

₱2,537,198.40

Progress

Reported complete (DPWH)

Start Date

July 2, 2019

Target End

October 28, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.