Buildings and Facilities18PE0093

CONSTRUCTION OF 4 STOREY 4 CLASSROOM 2 SCIENCE LAB 2 ICT LAB SCHOOL BUILDING AT EVELIO JAVIER MEMORIAL NHS, TUBA, BENGUET

CONSTRUCTION OF 4 STOREY 4 CLASSROOM 2 SCIENCE LAB 2 ICT LAB SCHOOL BUILDING AT EVELIO JAVIER MEMORIAL NHS, TUBA, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱26,912,527.35. Status: Reported complete (DPWH). Contractor on record: BALINTUGAN CONST 34566. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 34566

90 projects · ₱5.8B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS KENNON ROADKO228+067 - KO228+170KO229+090 - KO229+2

Cordillera Administrative Region, Cordillera Administrative Region

2020₱243.8M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, LABEY - LACAMEN PROVINCIAL ROAD (SECTION 4B)

Cordillera Administrative Region, Cordillera Administrative Region

2020₱234.2M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS, KENNON ROAD - K0223 + 749 - K0223 + 890TUBA, BEN

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF LENGTAN FLOOD CONTROL ALONG CHICO RIVER, SAMOKI, BONTOC, MOUNTAIN PROVINCE

Cordillera Administrative Region, Cordillera Administrative Region

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS BAGUIO - BONTOC ROADKO302+180 - KO302+300, KO314+

Cordillera Administrative Region, Cordillera Administrative Region

2021₱193.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIP, SLOPE COLLAPSE AND LANDSLIDES - PRIMARY ROADS, KENNON ROADKO234+910 - KO235+020, KO238+870 - KO238

Cordillera Administrative Region, Cordillera Administrative Region

2021₱173.7M
Reported complete (DPWH)
View all 90 projects →

4. Implementation

Contract Amount

₱26,912,527.35

Progress

Reported complete (DPWH)

Start Date

June 22, 2018

Target End

August 13, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.