Buildings and Facilities16DN0054

CONSTRUCTION OF FOUR (4) STOREY, TWELVE (12) CLASSROOM SUMILANG ELEM. SCHOOL, ANTIPOLO CITY, 2ND LD

CONSTRUCTION OF FOUR (4) STOREY, TWELVE (12) CLASSROOM SUMILANG ELEM. SCHOOL, ANTIPOLO CITY, 2ND LD is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱21,688,589.12. Status: Reported complete (DPWH). Contractor on record: PRECIOUS CONST 32995. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 32995

252 projects · ₱7.6B total · 0 flags

Other projects by this contractor

No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAMCONVERGENCE & SPECIAL SUPPORT PROGRAMCONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITYCONSTRUCTION OF 2ID PERIMETER FENCE AND GATE 1 & 2, PHASE 2,CAMP CAPINPIN, TANAY, RIZAL

Region IV-A, Region IV-A

2020₱127.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SALAPAN ELEMENTARY SCHOOL, SAN JUAN CITY

Metro Manila 1st DEO, National Capital Region

2024₱117.0M
Past target date (DPWH On-Going)
No sat.

CLUSTER 01: CONSTRUCTION OF NEW PUP CAMPUS IN CALOOCAN NORTH, BARANGAY 168, CALOOCAN CITYA. CONSTRUCTION OF NEW POLYTECHNIC UNIVERSITY OF THE PHILIPPINES, BARANGAY 168, CALOOCAN CITYB. CONSTRUCTION OF ADMINISTRATIVE BUILDING - POLYTECHNIC UNIVERSITY

Metro Manila 3rd DEO, National Capital Region

2023₱116.4M
Reported complete (DPWH)
No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS/NEW ROADS, TAGAYTAY CALAMBA ROAD VIA CANLUBANG, LAGUNA SECTION, LAGUNA

Region IV-A, Region IV-A

2020₱115.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ALERT MULTI-PURPOSE BUILDING BRGY. MALINTA, VALENZUELA CITY

Metro Manila 3rd DEO, National Capital Region

2020₱100.6M
Reported complete (DPWH)
No sat.

CLUSTER I :A) REPAIR/REHABILITATION/IMPROVEMENT OF LUZONG-TUQUIPA ROAD, BRGYS. LUZONG AND TUQUIPA, LUBA, ABRAB) REPAIR/ REHABILITATION/ IMPROVEMENT OF SITIO CABA-GAYAMAN ROAD, BRGY GAYAMAN, LUBA, ABRAC) REPAIR/REHABILITATION/ IMPROVEMENT OF SABNANGA

Cordillera Administrative Region, Cordillera Administrative Region

2018₱100.0M
Past target date (DPWH On-Going)
View all 252 projects →

4. Implementation

Contract Amount

₱21,688,589.12

Progress

Reported complete (DPWH)

Start Date

May 24, 2016

Target End

January 18, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.