Flood Control Structures, Waterway18LA0094

CONSTRUCTION OF REVETMENT BRGY. NAPNAPAN, PANTUKAN, COMPOSTELA VALLEY PROVINCE

CONSTRUCTION OF REVETMENT BRGY. NAPNAPAN, PANTUKAN, COMPOSTELA VALLEY PROVINCE is a DPWH-tracked public work in Davao de Oro 1st DEO, Region XI. Reported contract value: ₱33,893,961.94. Status: Reported complete (DPWH). Contractor on record: ALFREGO BUILDERS & SUPPLY. Figures trace to dpwh.

Davao de Oro 1st DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱33,893,961.94

Progress

Reported complete (DPWH)

Start Date

May 25, 2018

Target End

December 19, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.