Construction of Drainage Structure21LB0302

Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera. Talomo District, Davao City

Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera. Talomo District, Davao City is a DPWH-tracked public work in DAVAO DEL SUR, Region XI. Reported contract value: ₱9,800,000.00. Status: Reported complete (DPWH). Contractor on record: GRECO CONST AND SUPPLY. Figures trace to sumbong.

DAVAO DEL SUR, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱9,819,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Bago River, Sta. 2+370 to Sta.2+790, Davao City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010386

₱273,925,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007846

₱68,316,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014082

₱35,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012565

₱25,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010382

₱425,497,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008574

₱3,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROXI-21-0011208

₱882,831.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-ROXI-21-0011209

₱80,735.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0005360

₱5,000,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (DPWH)

Start Date

November 18, 2021

Target End

July 29, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.