Trust Funds 202121LH0163

CONSTRUCTION OF THE FOLLOWING PROJECTS AT BRGY. LAMANAN, CALINAN DISTRICT, DAVAO CITY, LGSF-BPD, ELCAC (1) REHABILITATION OF WATER SUPPLY SYSTEM AT BRGY. LAMANAN, DAVAO CITY (2) CONSTRUCTION OF ROAD AT PUROK 2B SITIO LIBONGAN, BRGY. LAMANAN, DAVAO CITY

CONSTRUCTION OF THE FOLLOWING PROJECTS AT BRGY. LAMANAN, CALINAN DISTRICT, DAVAO CITY, LGSF-BPD, ELCAC (1) REHABILITATION OF WATER SUPPLY SYSTEM AT BRGY. LAMANAN, DAVAO CITY (2) CONSTRUCTION OF ROAD AT PUROK 2B SITIO LIBONGAN, BRGY. LAMANAN, DAVAO CITY is a DPWH-tracked public work in Davao City 2nd DEO, Region XI. Reported contract value: ₱13,930,669.95. Status: Reported complete (DPWH). Contractor on record: NLC CONST AND SUPPLIES. Figures trace to dpwh.

Davao City 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction Flood Mitigation Structure protecting Daang Maharlika (MN) at Brgy. Bunawan, Davao City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Davao City 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱13,930,669.95

Progress

Reported complete (DPWH)

Start Date

September 26, 2022

Target End

January 30, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.