Roads18FF0040

FY-2018 NETWORK DEVELOPMENT-CONSTRUCTION OF BYPASS/DEVERSION ROADS, CONSTRUCTION OF JCT. NATO-SABANG COASTAL ROAD (SAGÑAY-TIGAON SECTION), STA. 0+500.00-STA.1+731.60, SAGÑAY AND TIGAONG, CAMARINES SUR

FY-2018 NETWORK DEVELOPMENT-CONSTRUCTION OF BYPASS/DEVERSION ROADS, CONSTRUCTION OF JCT. NATO-SABANG COASTAL ROAD (SAGÑAY-TIGAON SECTION), STA. 0+500.00-STA.1+731.60, SAGÑAY AND TIGAONG, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱92,634,205.98. Status: Reported complete (DPWH). Contractor on record: ALRO CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment and Channel Improvement at Barit River- Outfall (Bula and Nabua Section), Camarines Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0032622

₱0.00 · FY2018

Source

3. Procurement & Award

Confirmed (exact contract ID) · 100%

18FF0040 - Const. of Bypass / Diversion Roads

₱92,634,205.98 · ALRO CONSTRUCTION & DEVELOPMENT

Contractor

91 projects · ₱5.7B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES, BRGY. BUDIAO, DARAGA, ,ALBAY, DARAGA, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱184.5M
Past target date (DPWH On-Going)

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES, UPSTREAM OF CAMALIG BRIDGE, BRGY. 4 (POB)-QUIRANGAY, CAMALIG, ALBAY, CAMALIG, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱164.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO

Region V, Region V

2025₱159.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY BATANG, IROSIN, SORSOGON

Region V, Region V

2024₱158.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG GABAO RIVER, BARANGAY GABAO

Region V, Region V

2024₱158.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGO

Region V, Region V

2025₱154.3M
Past target date (DPWH On-Going)
View all 91 projects →

4. Implementation

Contract Amount

₱92,634,205.98

Progress

Reported complete (DPWH)

Start Date

May 6, 2018

Target End

March 2, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.