Flood Control and Drainage19AC0023

CONSTRUCTION OF FLOOD CONTROL ALONG ABRA RIVER (UPSTREAM), BANTAY, ILOCOS SUR

CONSTRUCTION OF FLOOD CONTROL ALONG ABRA RIVER (UPSTREAM), BANTAY, ILOCOS SUR is a DPWH-tracked public work in Ilocos Sur 1st DEO, Region I. Reported contract value: ₱29,400,000.00. Status: Reported complete (DPWH). Contractor on record: A P B CONST 17055. Figures trace to dpwh.

Ilocos Sur 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱29,400,000.00

Progress

Reported complete (DPWH)

Start Date

July 16, 2019

Target End

December 12, 2019

5. Audit