Roads20BB0021

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS-CONSTRUCTION OF CONCRETE ROAD-BAGUMBAYAN-CAMBONG-DAGUPAN ROAD LEADING TO CAGAYAN NORTH INTERNATIONAL AIRPORT, LAL-LO, CAGAYAN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS-CONSTRUCTION OF CONCRETE ROAD-BAGUMBAYAN-CAMBONG-DAGUPAN ROAD LEADING TO CAGAYAN NORTH INTERNATIONAL AIRPORT, LAL-LO, CAGAYAN is a DPWH-tracked public work in Cagayan 1st DEO, Region II. Reported contract value: ₱9,165,761.85. Status: Reported complete (DPWH). Contractor on record: JIRK CONST 29918. Figures trace to dpwh.

Cagayan 1st DEO, Region II
Region: Region II

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

DPWH ID 29918

54 projects · ₱433.7M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTER/QUARANTINE FACILITIES PUBLIC HEALTH FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER), BRGY. CENTRO, LAL-LO, CAGAYAN

Cagayan 1st DEO, Region II

2023₱49.5M
Reported complete (DPWH)
No sat.

CONST OF 2 STORIES-8 CL (2 UNITS) SB ELEM,JUNIOR&SENIOR HS(BATCH 3)STA.ANA FISHERIES NHS,STA.ANA,CAG

Cagayan 1st DEO, Region II

2016₱21.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY-CONSTRUCTION OF OTHER FACILITIES-CONSTRUCTION OF HEADQUATERS BUILDING (GROUP) , LAL-LO, CAGAYAN

Cagayan 1st DEO, Region II

2021₱18.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS-CONSTRUCTION OF CONCRETE ROAD - BAGUMBAYAN - CAMBONG - DAGUPAN ROAD LEADING TO CAGAYAN NORTH INTERNATIONAL AIRPORT, LAL-LO, CAGAYAN

Cagayan 1st DEO, Region II

2020₱17.1M
Reported complete (DPWH)
No sat.

CSSP - CONST/ IMPROVEMENT OF ACCESS RDS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM-KATUPARAN) - CONST OF CONCRETE ROAD - BAGUMBAYAN-CAMBONG-DAGUPAN LEADING TO CAGAYAN NORTH INTERNATIONAL AIRPORT, LAL-LO, CAGAYAN

Cagayan 1st DEO, Region II

2024₱14.7M
Reported complete (DPWH)
No sat.

CSSP - CONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITY (TATAG NG IMPRASTRAKTURA PARA SA KAPAYAPAAN AT SEGURIDAD PROGRAM - TIKAS) - CONSTRUCTION OF OTHER FACILITIES - CONSTRUCTION OF HEADQUARTERS, LAL-LO, CAGAYAN

Cagayan 1st DEO, Region II

2022₱14.7M
Reported complete (DPWH)
View all 54 projects →

4. Implementation

Contract Amount

₱9,165,761.85

Progress

Reported complete (DPWH)

Start Date

June 29, 2020

Target End

October 6, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.