Buildings and Facilities19HB0097

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ILAUD, PILAR, BOHOL

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ILAUD, PILAR, BOHOL is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱484,869.53. Status: Reported complete (DPWH). Contractor on record: CLAVITE CONST AND SUPPLY 40502. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 40502

93 projects · ₱442.3M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS, CARMEN, BOHOL, SEC. 1 : STA. 0+000 - STA. 0

Bohol 3rd DEO, Region VII

2024₱34.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL HIGHWAY ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. POBLA

Bohol 3rd DEO, Region VII

2022₱29.4M
Reported complete (DPWH)
No sat.

BASIC EDUCATIONAL FACILITIES FUND (BEFF)- BATCH 1: CONSTRUCTION OF 2STY6CL SCHOOL BUILDING, CANMAYA DIOT HIGH SCHOOL, SAGBAYAN, BOHOL

Bohol 2nd DEO, Region VII

2023₱20.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND / OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR / STRATEGIC PUBLIC BUILDING / FACILITIES - CONSTRUCTION OF ROAD, SITIO KAWASAN

Bohol 3rd DEO, Region VII

2022₱19.6M
Reported complete (DPWH)
No sat.

COMPLETION OF ALBURQUERQUE PUBLIC MARKET

Bohol 1st DEO, Region VII

2019₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - JCT. (LIR) BUENOS AIRES-NUEVA VIDA (

Bohol 3rd DEO, Region VII

2024₱14.7M
Reported complete (DPWH)
View all 93 projects →

4. Implementation

Contract Amount

₱484,869.53

Progress

Reported complete (DPWH)

Start Date

June 26, 2019

Target End

July 25, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.