Buildings and Facilities24F00363

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUIDING (SENIOR CITIZENS CENTER), BASUD, CAMARINES NORTE, BASUD, CAMARINES NORTE (2N

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUIDING (SENIOR CITIZENS CENTER), BASUD, CAMARINES NORTE, BASUD, CAMARINES NORTE (2N is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱6,325,470.42. Status: Past target date (DPWH On-Going). Contractor on record: MAN CONST SUPPLY. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

15 projects · ₱95.6M total · 0 flags

Other projects by this contractor

No sat.

LOCALLY-FUNDED PROJECTS-NATIONAL BUILDING PROGRAM-BUILDINGS AND OTHER STRUCTURES-MULTIPURPOSE/FACILITIES-CONSTRUCTION OF DPWH CAMARINES NORTE-SUB DEO (QAS)MATERIALS TESTING LABORATORY BUILDING, F. PIMENTEL AVENUE, DAET, CAMARINES NORTE, DAET, CAMARINES NO

Region V, Region V

2025₱24.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM-ROLL-IT)-BRGY. FABRICA ROAD CONNECTING DAAN

Region V, Region V

2023₱14.5M
Reported complete (DPWH)
No sat.

CAPITAL OUTLAY-DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP)-COMPLETION/UPGRADING/REPAIR AND EQUIPPING OF RHUS-DAET RURAL HEALTH UNIT III, CAMARINES NORTE, DAET, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱6.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-BIP-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUIDING (SENIOR CITIZENS CENTER), SAN LORENZO RUIZ, CAMARINES NORTE, SAN LORENZO RU

Region V, Region V

2024₱6.3M
Past target date (DPWH On-Going)
No sat.

CAPITAL OUTLAY-DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP)-COMPLETION/UPGRADING/REPAIR AND EQUIPPING OF RHUS-MERCEDES RURAL HEALTH UNIT II, BRGY. GABOC, CAMARINES NORTE, BRGY. GABOC, MERCEDES, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱5.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD PUROK 3 SITIO CATAROG BARANGAY ANGAS, BA

Region V, Region V

2024₱4.8M
Past target date (DPWH On-Going)
View all 15 projects →

4. Implementation

Contract Amount

₱6,325,470.42

Progress

Past target date (DPWH On-Going)

Start Date

November 22, 2024

Target End

April 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.