Flood Control and Drainage24K00177

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IPONAN RIVER, PACKAGE 8, CAGAYAN DE ORO CITY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IPONAN RIVER, PACKAGE 8, CAGAYAN DE ORO CITY is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱146,877,996.76. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: EQUI-PARCO CONST CO. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱146,877,996.76

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 3, 2024

Target End

May 27, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.