Buildings and Facilities22CF0115

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANGITAN WEST, CABANATUAN CITY, NUEVA ECIJA

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANGITAN WEST, CABANATUAN CITY, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱9,702,083.21. Status: Reported complete (DPWH). Contractor on record: D B BARAQUIEL CONST. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure in Barangay Buliran, San Antonio, Nueva Ecija
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Nueva Ecija 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

52 projects · ₱610.3M total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION PROGRAM 7-REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - JOSE ABAD SANTOS AVE (JASA) - K0 097+(-881) - K0 097+000, K0 097+000 - K0 097+180, K0 098+000 - K0 098+066, K0 101+728.60 - K0 101+1003, K0 1

Nueva Ecija 2nd DEO, Region III

2024₱68.7M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURE / FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURES ALONG PEÑARANDA RIVER, BARANGAY SINASAJAN (RIGHT), PEÑARANDA, NUEVA ECIJ

Nueva Ecija 2nd DEO, Region III

2023₱48.0M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG PEÑARANDA RIVER, BARANGAY STO. TOMAS, PEÑARANDA, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2023₱47.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

Construction of Flood Control Structure along Pampanga River, Barangay Bagong Sikat, Cabiao, Nueva Ecija

CABIAO (NUEVA ECIJA), NUEVA ECIJA, Region III

2023₱28.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION / IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CONCRETING OF ACCESS ROADS LEADING TO MINALUNGAO NATIONAL PARK, SAN ISIDRO, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2025₱26.7M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. CONCEPCION, CABIAO, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2024₱24.4M
Reported complete (DPWH)
View all 52 projects →

4. Implementation

Contract Amount

₱9,702,083.21

Progress

Reported complete (DPWH)

Start Date

April 11, 2022

Target End

January 5, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.