Roads24FO0089

CONCRETING OF BRGY. GUMIAN-BATBAT FMR, BRGY. GUMIAN-BATBAT, GUINOBATAN, ALBAY

CONCRETING OF BRGY. GUMIAN-BATBAT FMR, BRGY. GUMIAN-BATBAT, GUINOBATAN, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱14,248,302.30. Status: Past target date (DPWH On-Going). Contractor on record: TRIPARTITE ENGINEERING AND CONST. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tobgon Flood Mitigation Structure, Ligao City, Albay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Albay 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

11 projects · ₱195.3M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN)-GUINOBATAN-JOVELLAR-DONSOL ROAD LEADING TO PILAR PORT, GUINOBATAN AND JOVELLAR, ALBAY

Albay 3rd DEO, Region V

2025₱110.0M
Past target date (DPWH On-Going)
No sat.

CONCRETING OF SITIO MAWASWAS, BATBAT TO ONGO FMR, GUINOBATAN, ALBAY

Albay 3rd DEO, Region V

2024₱14.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF BRIDGE AND APPROACHES IN

Albay 3rd DEO, Region V

2024₱9.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, PINAGLABANAN NATIONAL HIGH SCHOOL, BARANGAY PINAGLABANAN, GOA, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2025₱9.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM- TRIP)- SAN ISIDRO- FLORISTA- PANOYPOY- BASCARAN LEADING TO BICOL INTERNATIONAL AIRPORT AND DO

Albay 3rd DEO, Region V

2025₱9.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF SINUNGTAN-PALANAS ROAD, GUINOBATAN, ALBAY

Albay 3rd DEO, Region V

2024₱9.1M
Past target date (DPWH On-Going)
View all 11 projects →

4. Implementation

Contract Amount

₱14,248,302.30

Progress

Past target date (DPWH On-Going)

Start Date

July 15, 2024

Target End

December 26, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.