CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE II), BARANGAY POBLACION, MAIGO, LANAO DEL NORTE

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (PHASE II), BARANGAY POBLACION, MAIGO, LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 1st DEO, Region X. Reported contract value: ₱29,363,921.78. Status: Past target date (DPWH On-Going). Contractor on record: NDP CONST DEVELOPMENT 39524. Figures trace to dpwh.

Lanao del Norte 1st DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Maigo Bridge (B00949MN), Package 1, Maigo, Lanao del Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Lanao del Norte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱29,363,921.78

Progress

Past target date (DPWH On-Going)

Start Date

January 21, 2025

Target End

September 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.